Construction adjudication is built on a simple principle: pay now, argue later. Courts enforce adjudication decisions quickly and with very little appetite for challenge. Challenges to enforcement succeed so infrequently that the courts regularly say so out loud. A June 2026 ruling from the Technology and Construction Court is significant precisely because it is one of those rare occasions where the challenge worked. But the more important question is not why the court refused enforcement in this case. It is what that refusal tells the industry about where the line actually sits, and why the bar remains as high as it does.
The pay now, argue later principle
Adjudication was introduced under the Housing Grants, Construction and Regeneration Act 1996 as a fast, binding and mandatory dispute resolution mechanism for construction contracts. Its purpose was to keep cash flowing through projects by resolving payment and other disputes quickly, rather than leaving parties locked in litigation for years. An adjudicator’s decision is temporarily binding and must be complied with immediately, but either party can have the underlying dispute finally determined in court or arbitration if they wish.
The courts enforce adjudication decisions with a strong presumption in favour of compliance. A losing party who attempts to use natural justice arguments as a means of avoiding or delaying payment, rather than pursuing a genuine procedural unfairness, faces openly declared scepticism. The judge in Premier Modular v Maidstone and Tunbridge Wells NHS Trust acknowledged that scepticism directly before going on to explain why, in this particular case, it was overridden.
Natural justice in this context means that an adjudicator must act fairly: both sides must have a proper opportunity to present their case and to respond to the case against them, and the adjudicator must not decide the dispute on a basis that neither party had a chance to address. The courts have identified two main types of natural justice challenge: where an adjudicator has failed to consider a party’s defence, and where the adjudicator has decided the dispute on a basis the other side had no proper opportunity to deal with. It is the second type that arose here, and it is where the real interest lies.
What happened
Premier Modular Limited was engaged by Maidstone and Tunbridge Wells NHS Trust under an NEC4 Option A contract worth just under £19.8 million to design and construct a new barn theatre at Maidstone Hospital. A barn theatre is an open-plan surgical space in which multiple patients are treated simultaneously, and the project was the first of its kind in the UK. During the works, a dispute arose about the availability of a permanent mains water supply. Premier Modular’s position was that the Trust was required to make it available by 30th October 2023 for testing and commissioning, and that the Trust’s failure to do so until February 2024 caused significant programme delay. The Trust accepted responsibility for the water supply but denied that any particular date had been agreed for its provision.
Under an NEC4 contract, a contractor can claim additional time and money where a defined compensation event occurs, which is a specific circumstance the contract recognises as justifying a change to the price or programme. Premier Modular referred the dispute to adjudication, arguing that the Trust’s failure constituted a compensation event under three specific clauses. The adjudicator found in Premier Modular’s favour and awarded approximately £1.65 million. When the Trust declined to pay, Premier Modular applied to the Technology and Construction Court for summary enforcement of the award.
The reason lies in what the adjudicator actually did. During the adjudication, he asked the parties a clarifying question about the status of a later programme revision. Although the clarification request reproduced clause 60.1(3), the judge held that it did not ask the parties to address whether that provision applied. It asked about the status of a particular programme revision, which both parties agreed was not an Accepted Programme. Both parties had proceeded on the common understanding that the original Accepted Programme was the applicable one, and neither had relied on any compensation event clause beyond those identified in Premier Modular’s referral. In his decision, however, the adjudicator found that the Accepted Programme had been updated, that a different compensation event provision from any that either party had argued applied, and that Premier Modular was entitled to its award on that basis. Premier Modular had not advanced that case. The adjudicator had constructed it for them, on grounds the Trust had never had a proper opportunity to address.
Speed, pressure and the temptation to find the right answer
Before examining how the court analysed that conduct, it is worth understanding the environment in which it occurred, because the broader tension this case illustrates is not unique to this adjudicator or this dispute.
Adjudication is fast by design. Adjudicators are expected to resolve complex, high-value disputes within weeks, typically 28 days from referral unless extended by agreement. On an NEC4 project worth nearly £20 million, with disputes about compensation events, programme management and contractual notification requirements, that is a genuinely demanding timetable. The process also gives adjudicators significant powers to take an active role in resolving the dispute, including seeking clarifications, requesting further submissions and drawing their own conclusions on the material before them. Most adjudicators navigate all of that without producing decisions that stray outside the parties’ cases. But the combination of time pressure and those broad powers creates conditions in which the temptation to pursue what an adjudicator believes to be the correct contractual answer, even where neither party has argued it, can arise.
That temptation is understandable. It is also, as this case confirms, one that adjudicators need to resist. The procedural safeguards of adjudication exist precisely because the process is fast. Speed is its strength, and it is also its vulnerability. An adjudicator who identifies a new basis for their decision during the proceedings must put it to the parties and give them a genuine opportunity to engage with it before deciding on it. Speed does not justify bypassing that requirement. For parties, the practical lesson is equally direct. Pay close attention to what an adjudicator is doing during the process, not just at the decision stage. A clarification question that seems to be moving toward a basis neither party has argued is the moment to engage, not the decision itself.
Disagreeing with both parties is fine. Inventing a third case is not
The judgment draws a precise distinction that is worth understanding clearly.
An adjudicator is not a passive referee. They are fully entitled to reach conclusions that differ from both parties’ positions, disagreeing with their analysis, applying the contract differently from how either party argued it, or preferring one party’s evidence without accepting all of it. None of that is a breach of natural justice. Mere mistakes, poor reasoning, misunderstandings of the arguments or incorrect conclusions do not make a decision unenforceable. The pay now, argue later principle is robust enough to absorb those imperfections, and the courts have said so consistently.
The line is crossed when an adjudicator goes off on what the courts call a frolic of their own, meaning they decide the case on a basis that was never argued by either party, without first giving them a fair opportunity to address it. That is not an adjudicator exercising independent judgment on the material before them. It is an adjudicator deciding the dispute on an unargued basis without giving the parties a fair opportunity to address it. The party’s right to a fair process is not satisfied by an opportunity to address the arguments that were advanced against them. It requires an opportunity to address the arguments the adjudicator is actually going to decide on.
In Premier Modular, the adjudicator appears to have identified what he considered the correct contractual route to the answer and followed it. The judgment reinforces that a broadly drafted notice of adjudication may establish jurisdiction over the dispute, but it does not give an adjudicator free rein to decide that dispute on grounds neither party has advanced. Those are different questions, and confusing them is what cost Premier Modular its enforcement.
This does not lower the bar. It confirms how high it is
One risk in reporting cases like this is that construction professionals read them as a signal that natural justice challenges are becoming more viable. That reading would be wrong, and the judgment itself resists it.
The court spent considerable time explaining what does not constitute a breach of natural justice. An adjudicator who misunderstands a party’s case, confuses two different contractual provisions, reaches a conclusion that feels surprising or unsupported, or fails to deal with every argument advanced is not acting unfairly in the legal sense. Those are not grounds for resisting enforcement. They are the normal imperfections of a process deliberately designed to produce fast decisions on complex disputes, and the courts have consistently refused to treat them as sufficient. The Trust’s separate natural justice complaint—that the adjudicator had failed to address its notification defence—was rejected. He had addressed that issue, even if he may have misunderstood the defence or confused the contractual provisions. That was not, without more, a breach of natural justice.
What made this case exceptional was the combination of two specific failures. The adjudicator decided the case on a contractual provision that nobody had argued. He also made a factual finding about the Accepted Programme that directly contradicted the agreed position of both parties. Together, they produced a decision that the Trust had no real opportunity to address on its actual basis, and that was a materially different case from those the parties had advanced. The judge described the outcome as obvious unfairness. Obvious is the operative word. The court was not conducting a fine-grained review of the adjudicator’s reasoning. The departure from the parties’ cases was clear enough to be apparent without close analysis.
Premier Modular v Maidstone and Tunbridge Wells NHS Trust will not open the floodgates to natural justice challenges. The court was explicit that this was one of those rare cases, and the facts that made it rare are precisely identified in the judgment. But it is a clear and useful marker of where the boundary between legitimate adjudicator independence and an unenforceable frolic actually lies. For parties who find themselves in an adjudication where the process appears to be moving in an unexpected direction, the message is to engage early and directly. For those reviewing a decision that rests on grounds they never had the chance to address, the message is to take advice quickly. And for the industry more broadly, the case is a reminder that adjudication’s speed is both its defining strength and the source of the pressure that, occasionally, causes it to go wrong.